Downtown Dripping Springs: Stephenson Delays & Christmas on Mercer 2026

At the corner where Old Fitzhugh Road meets Mercer Street, a two-story school building from 1939 has been sitting behind barricades for a year. It was a high school through 1949. It went on the National Register of Historic Places in 2013. Since October 2025 it has been a job site, and the city's own paperwork gave that job site a firm end date of October 20, 2026.

Earlier this month, the city wrote that "recent delays" had changed that timeline. The Stephenson and the projects planned around it are meant to turn downtown into a place built for gatherings, with a powered event lot, a shaded walkway, and a performance hall. This holiday season, downtown keeps the event layout it has used for years, and the city has prepared for the Stephenson corner to still be a construction zone on December 5.

A Contract Clock That No Longer Holds

The City Council approved a $4.89 million construction contract for the Stephenson on October 7, 2025, with QA Construction as the general contractor. Community Impact reported that the restored building would become a community performance center for meetings and performances, with some civic and community offices inside. Officials broke ground on October 23, 2025.

As late as the city's June 16, 2026 budget workshop, the project was listed as "Under Construction" on a 365-day timeframe ending October 20, 2026.

The schedule changed in a document you wouldn't expect to carry construction news. It's the October 6 staff report on street closures for Christmas on Mercer, prepared by the city's community events coordinator, and it says plainly:

"Completion was expected by the start of the 2026 COM event, however recent delays have altered the projected timeline."

That line comes from the October 6, 2026 Christmas on Mercer staff report. It gives no new completion date. A March staff report had listed an expected opening date of "10/26," and no revised opening date or booking process has been announced since the delays.

A Parking Lot Wired for Festivals

The building is only half of the project. The Stephenson and a new downtown public parking lot were permitted, bid, and awarded together, and the same general contractor is building both. A March 2, 2026 staff report put substantial completion in October 2026.

The same report shows what the lot is for. It's getting hard-wired lighting and 12 electrical receptacle stubs, enough to power civic festivals and events, and possibly a permanent farmers market. Community Impact also reported that the expanded lot would hold more than the old one and leave room for community events and markets.

The farmers market idea is written into city planning. The parks department's FY2027–FY2031 strategic plan lists "Consider moving the Farmers Market to the Stephenson building parking lot" as an initiative. No move has been announced.

For now, Wednesday afternoons stay the same. The city calendar lists the Dripping Springs Farmers Market from 3:00 to 6:00 p.m. at the Vendor Hall at Dripping Springs Ranch Park & Events Center, 1042 Event Center Dr. If you're headed there in late October, you'll find it out at Ranch Park.

The Paseo Arrives in Pieces

The Mercer Street Paseo is the walkway that connects the new lot and building to the shops on Mercer. Community Impact described it in April as a pedestrian path between Vintage Soul and the downtown public restrooms, linking to the Stephenson, with an ADA-compliant sidewalk, lighting, shade trees and drainage.

It also ran into a budget problem. The paseo has $200,000 approved through the city's TIRZ. In July 2026, staff tried to add the whole paseo to the Stephenson contract as a change order. The quotes came back at more than double the budget, so the city split the work into three phases, as laid out in the October 6 engineering staff report.

Phase Budget What it covers Who builds it
Phase 1 $49,995 Dumpster enclosure, paving for trash truck turns, curb and sidewalk tie-ins at the Stephenson site Added to the Stephenson contract in July 2026
Phase 2 $85,400 base bid Underground utilities, storm drains, tree wells, light pole foundations, the sidewalk itself S&D Constructors, Inc., recommended for a $100,000 award
Phase 3 $64,605 Plantings, crushed granite, benches, paver step stones, light poles, wiring City crews plus a landscape contractor "at a later date"

The $100,000 Phase 2 recommendation includes a $14,600 allowance, which can pay for some Phase 3 finish items while the Phase 2 crew is already on site.

Staff planned to execute the Phase 2 contract on October 16, issue notice to proceed on Monday, October 19, and finish construction in early December. Phase 2 bid documents call for barricades, signs and traffic handling over two months. They don't spell out specific street closures or parking changes.

Put those dates next to the holiday calendar. The walkway's underground work and sidewalk are scheduled to wrap up in the same week as downtown's biggest Saturday. The benches and plantings that would make it a place to linger are on no schedule yet.

Two Saturdays on Mercer

The season starts with the city's free Tree Lighting & Holiday Movie! at Veterans Memorial Park, known locally as The Triangle, at 160 Mercer Street, starting at 5:00 p.m. The city calendar listing gives the date as Saturday, November 28, 2026, but the description underneath says November 29. Check the listing again closer to Thanksgiving weekend before you plan around either day.

One week later comes Christmas on Mercer on Saturday, December 5. It's the event's 22nd year, organized by the Dripping Springs Lions Club and the City of Dripping Springs. The city calendar lists a 10:00 a.m. start, and the 2026 vendor booth form sets booth hours at 10 a.m. to 5 p.m., with arts and crafts, business booths and photo opportunities.

The full 2026 lineup hasn't been posted. Last year's gives a good idea of the day. Community Impact's preview of the 2025 event listed free admission, games, food booths, local vendors, live music, pony rides, train rides and a giant snow globe, with Santa arriving on a fire truck before pictures.

Road closures start at 5:00 a.m. on December 5, long before the first booth opens:

Street Closed section
Mercer Street From Bluff Street up to and including Wells Fargo Bank
San Marcos Street From Mercer to Wallace Street
College Street From the rear parking lot entrance of Mazama Coffee to Mercer
Old Fitzhugh Road Closed to through traffic at Ranch Road 12, fully closed from the Stephenson lot at 101 Old Fitzhugh Rd. to Mercer

If you live off Old Fitzhugh or usually cut through from RR 12, that last row matters most. Plan to leave early or take another route that morning.

The Corner That Decides the December Map

According to the street closure report, the Lions Club didn't change its layout for 2026, and the traffic plan builds on ones the city has used successfully before. The one open question is the Stephenson corner. In 2025 the city put up extra safety barricades at 101 Old Fitzhugh Rd. to secure the construction area. For 2026, staff drew up two maps, one with those added barricades and one without, and recommended that the final choice depend on the state of the Stephenson site on event day.

Here's the fall sequence, using the city's own planned dates:

  1. October 16: Paseo Phase 2 contract execution, per staff schedule
  2. October 19: Planned notice to proceed for paseo Phase 2
  3. October 20: Original end date of the Stephenson contract, now delayed
  4. November 28: Tree Lighting & Holiday Movie at The Triangle, per the calendar's event date
  5. December 5: Christmas on Mercer, closures from 5:00 a.m.
  6. Early December: Planned completion of paseo Phase 2

The powered lot, the possible farmers market move and the performance hall all wait on a finish date the city hasn't published. This December, the Old Fitzhugh end of the festival will have barricades or open pavement depending on how far QA Construction gets by the first Saturday of the month, and the city will pick between its two maps based on that.

Downtown's growing pains are easier to plan around with someone who keeps up with the council agenda for you. If you're weighing a move to Dripping Springs, or you're curious how the Stephenson and Mercer Street projects might shape your own corner of town, Bailey Group is glad to talk it through. Schedule Your White‑Glove Consultation.

Work With Us

Our expansive network and white-glove service ensure a bespoke experience for both buyers and sellers. Let our top producing team find your dream home today.

Follow Me on Instagram